Get in touch with JA Construction Site Services Ltd for professional building services in Northamptonshire, the Midlands and the surrounding areas. Whether you’re planning a small domestic project or a large-scale commercial development, our experienced team is here to provide expert advice and tailored solutions to suit your specific requirements. We are committed to delivering reliable support throughout every stage of your build, ensuring smooth and efficient project completion. For your convenience, we accept BACS payments, making transactions easy and secure. Contact us today to discuss your needs—our specialists are ready to assist with expert foundations and piling solutions designed to meet the unique demands of your site.

RECENT PROJECTS

Bridgewater Somerset - 2nd Phase Pilling Job

This was the 2nd phase of a piling job we installed 8no screw piles on to support a newly installed gas pile which was being upgraded from an older one exsisting pipe that was in need of some TLC.  

Installing time scales were 2no days with a 3man piling team and 1no 13t excavator and specialist piling equipment

No Images Found!

Cambridge Helical Pilling Job

Helical piles were used due to the speed and the reduction of the Carbon footprint they offer compared to other types of foundations.  

Installation timeframe was 4no days onsite and was carried out with a 3 man piling crew and 1no 13t excavato’

No Images Found!

Norfolk Vangaurd 400 KVA Substation - Helical Pile Installation

No Images Found!

Kirkstall Platform Extension - Installation Of Kite System

No Images Found!

Kirkstall Platform Extension - Installation Of SME Foundations

As part of the project we undertook the installation of SME foundation behind the newly extended platform extension.

The works consisted of 6 number concrete strip foundation running approximately 32m long and 2.8m wide.

Timber shutters were manufactured by our operatives onsite along with the reinforcement cages.

Work duration was 4 weeks from start to finish.

No Images Found!

Kirkstall Platform Extension - Installation Of Kite System

The project consisted of installing 54 concrete caps along with 162 Grundomat piles 220mm diameter and to a depth of 6m.

The programme of works was 14 weeks long and consisted of midweek and weekends.

Grundomat piles were installed using 2 x 180mm diameter moles assisted by 5 ton excavators.

Concrete caps were produced using specialist steel shutters specifically manufactured for the project, these also acted as temporary works when installed in close proximity to the running line.

No Images Found!

No Images Found!